TRAIN passengers from Blaenau Ffestiniog could potentially be without their main railway link for more than two months.

Network Rail engineers are continuing repair work on the Conwy Valley line after flooding caused damage at over 100 separate locations.

The severe flooding has meant trains have been unable to run between Llandudno Junction and Blaenau Ffestiniog since 27 December last year.

Current deadlines suggest that Blaenau Ffestioniog will be without the arterial north Wales route until the end of February.

However, the wait may be even longer if further flooding takes place.

The Conwy Valley saw unprecedented rainfall in December which severely damaged sections of the railway, washing out hundreds of tonnes of ballast – the crushed rock that helps to hold the track in place.

Flood waters reached platform level at North Llanrwst station, overwhelmed banks alongside the railway and caused considerable damage to a number of bridges along the route.

The lack of train service has left the Meirionnydd town feeling “isolated” according to local Gwynedd councillor Annwen Daniels in a recent interview.

Work to reopen the line is ongoing as engineers have been on site undertaking detailed investigations to understand the full scale of the damage.

Sections of the line remained underwater in the days following the flooding and more damage to signalling cables was discovered as debris was removed­.

Network Rail is “working hard” to rebuild the damaged railway, repair bridges, secure embankments, replace signalling cable and clear away debris.

Network Rail Wales route managing director Paul McMahon said: “The Conwy Valley saw record rainfall in December and this has caused a huge amount of damage to the railway.

“We know how important the line is for the local community and we’re working hard to repair the damage and get the line reopened as soon as it’s safe to do so.

“We have started work to repair the damage caused by the flooding, including replacing the hundreds of tonnes of ballast that were washed away. The ground conditions are still far from ideal and this is causing us challenges in accessing the sites.

“There’s also the risk of further flooding given how wet the land is.

“In the meantime, I’d like to thank local people for their patience and ask passengers to check with National Rail Enquiries or Arriva Trains Wales before they travel.”

While work to repair the Conwy Valley line continues, rail replacement buses are in operation.